Last Sunday (Mar 28), train services between Punggol and Serangoon stations on the North East Line (NEL) were disrupted due to a power fault at Buangkok station. But how is the North East Line powered differently compared to other MRT lines in Singapore? MRT trains are powered using Electricity All 6 MRT lines in Singapore READ MORE »
News
Singapore’s Integrated Train Testing Centre to be Completed in 2024
In a Facebook post by the Land Transport Authority (LTA) on 17 March 2021, the Integrated Train Testing Centre (ITTC) has commenced civil construction works with a groundbreaking ceremony officiated by Minister for Transport Ong Ye Kung. The ITTC is the first of its kind in Southeast Asia, with a dedicated facility that will be READ MORE »
Full Sunday Closure of Selected East-West Line Stations – March & April 2021
To facilitate Cable Replacement Works along the Tuas West Extension (TWE), selected MRT stations along the East-West Line (EWL) will be closed on Sundays from 14 March to 18 April 2021. SMRT mentions that as part of precautionary measures to be implemented against power cable faults and potential train service disruptions, about 150km of 22kV will READ MORE »
Groundbreaking for Singapore-Johor Bahru RTS Link
Construction for the Rapid Transit System (RTS) linking Singapore and Johor Bahru (Malaysia) officially began following a groundbreaking ceremony held at Woodlands North in Singapore on Jan 22. Present during the event was Transport Minister Mr. Ong Ye Kung. About the RTS The RTS is 4km long connecting Woodlands North (Singapore) and Bukit Chagar (Johor READ MORE »
Changes to Thomson-East Coast Line Operating Hours from January to April 2021
Early Closure and Late Opening arrangements for the Thomson-East Coast Line (TEL) will be extended till 30 April 2021 for additional testing hours for the system integration with Stage 2 of the line. Additionally, the second stage of the Thomson East Coast-Line (TEL2) was originally scheduled to open by the end of 2020. However, due READ MORE »
Train & Bus Service Extension on New Year’s Eve (31 Dec 2020)
Selected train and bus services will be extended on the night of 31 December 2020 (Thursday) for New Year’s Eve. Do take note of the extended service hours and plan your journeys if you are travelling late on the night of 31 December 2020.
Opening of TEL2 revised to Q3 2021
The second stage of the Thomson-East Coast Line (TEL2) faces further delays to its opening schedule. This is the second revision for the opening schedule for TEL2, where it is now planned to open by Q3 2021, pushed back from the first revision of Q1 2021. Land Transport Authority (LTA) mentioned in a Facebook post READ MORE »
Changes to Thomson-East Coast Line Operating Hours from November to December 2020
Early Closure and Late Opening arrangements for the Thomson-East Coast Line (TEL) will be extended till 31 December 2020 for additional testing hours for the system integration with Stage 2 of the line. The shorter operating hours were initially till 30 August, and then extended to 1 November. The second stage of the TEL was READ MORE »
Bombardier C951 Train Upgrade
Bombardier Transportation (BT), the original manufacturer of the Downtown Line (DTL) rolling stock, has recently won a contract from Singapore’s Land Transport Authority (LTA) to revitalise critical systems on the Bombardier C951 trains. History of the Bombardier C951 Train First delivered in 2012, the trains are quickly becoming antiquated as compared to recent rolling stock READ MORE »
40 additional new trains for NSEWL
, 40 additional R151 trains will be purchased for the North-South and East-West Lines, replacing 19 sets of 2nd-generation Siemens C651 and 21 sets of 3rd-generation Kawasaki-Nippon Sharyo C751B trains. The 40 additional new trains will adopt the same design as the initial orders, allowing engineers to be familiarised with a single train model, enhancing READ MORE »